· We were guided by Mr. Irwan in to the production line
· Follow Toyota system of assembling which is line time accuracy.
· From 1985 they following the same system of operation .now currently they using 5.72 man Hr/unit
Trim and final shop process plan
· 1st the empty body will enter the conveyor line
· Production line output capacity is around 150 k/year
· Currently they were producing car model num:P2-11 A/ P2-11C.called as proton saga FL
· Average output is 40 unit / hour
· Current l\line speed is 38 unit / hour
· It takes around 94.7sec /unit
· The line efficiency is 95%
· Total process time is 19.234 sec for each process
· Man power is 207 workers directed by 63 supervisor
· They are using 1424 system to monitor each station .
· Its like 1 supervisor , 4 team leader , 24 man power.
· Tanjong malim plant is working on 60% automation system and hicom sha alam plant is 30% automated system.
· Stamping , body assembly , painting and trim and finalization is the main process a car will go thru.
Wagon dolly system
· It’s a system where they will manage their components on their station.
· It’s a system where replacing the finished part without any disturbance to the workers.
· Its working on time basis method.
· Every 15 min the fitter will purchase new product to their station.
· If he cant finis his work on given time, the next station worker will help him doing his job done.
· For a new fitter or operator , at least he will follow his supervisor for one week.
· He will not do any work just observation only for the entire week.
· Every end process have a gate.
· There they will have a QC check.
· They using the FIFO (First In First Out) system to monitor the quality of the product they make.
The encouragement they provide for the workers.
· To encourage their worker, the management have given prizes to the designer who design a system where its help the worker to reduce their work load.
· Example: like a worker need to bend down every time to fit their part in the car, so they design a pulley system where it will bring the required part near to the worker so that he wont to bent down to do the task every time.
· It also reduce the risk and the work load of a worker. Other than that its also save the time consume by each process.
Satellite line
· In this line, they are doing face out units for small orders like for government order.
· They are capable to produce 4 units per hour.
Sub line
· In this line they were fitting engine and transmission compartment for the car.
· In this line they also fit the gear system also.
· In engine docking area, two person will work on this part.
· Both also must work synchronously to mount the engine to the correct position.
· Each person works under 95 sec to finish their task. So times by 2 equal to 190 sec.